Forest Hill Silos Mural Project

Project Overview

Lockyer Valley Regional Council has been working on a project for a large scale mural on the GrainCorp silos adjacent to the rail line in Forest Hill.

In 2021, Council provided an opportunity for the Forest Hill community, the wider Lockyer Valley Region, as well as potential visitors, to give their ideas on design themes for the artwork. Community feedback was collated and analysed (see the Document Library) and used to prepare a design brief for prospective artists to submit a design and competence portfolio.

Council's latest consultation in April and May 2023 involved seeking community feedback on the Viewing Precinct. Submissions from the community were collated and reviewed, and the Consultation Report is available in the Document Library.

Construction works

Council crews will soon commence work on the viewing precinct for the future murals in the GrainCorp Forest Hill Silo Art Project in Railway Street, Forest Hill. These works will deliver:

  • silos viewing area
  • visitor carpark, including long vehicle parking
  • coach setdown
  • footpaths
  • landscaping
  • seating area
  • shaded facilities
  • asphalt pavement works on Railway Street.

Traffic management will be in place as required throughout the duration of the works.

This project has received $1.85 million in funding through the South East Queensland (SEQ) Liveability Fund, one of 29 commitments under the SEQ City Deal – a $1.8 billion partnership between the Australian Government, Queensland Government and Council of Mayors (SEQ) to deliver long-lasting benefits for the fast-growing SEQ region.

Viewing and Parking Area Works

Council crews will soon commence work on the viewing precinct for the future murals in the GrainCorp Forest Hill Silo Art Project in Railway Street, Forest Hill. These works will deliver: silos viewing area visitor carpark, including long vehicle parking coach setdown footpaths landscaping seating area shaded facilities asphalt pavement works on Railway Street. Traffic management will be in place as required throughout the duration of the works. This project has received $1.85 million in fundi...

Consultation Analysis Report Now Available

The consultation report for the Viewing Precinct is now publicly available, and can be found in the Document Library. Thank you to everyone who took the time to submit feedback for the project. Community consultation indicated strong support for the project, with Council taking on board the feedback received and adjusting some aspects of the design. Council will now proceed to detailed design stage. Please note Council are yet to request Expressions of Interest from artists, but will provide ano...

The Forest Hill silos were constructed to meet the increase in production of wheat and barley on the Lockyer Valley and surrounding districts in the 1970s. Its location between Toowoomba and Brisbane and accessibility to the rail line made it the ideal location. 

Construction commenced on the first two silos on 13 January 1975 in a non-stop concreting process that lasted two days and involved 45 men for each 12-hour shift. Holding 2,200 tonnes each, the cost of this project was $200,000. These are the two central silos. 

The two outside silos were constructed in 1979 to respond to the high demand and traffic congestion caused by waiting trucks. The work took 20 men four days to complete, taking the total capacity of the four silos to 8,800 tonnes. 

Grain production and storage has decreased since the boom years of the 1970s and 80s and the silos transitioned to holding sites for companies including Uncle Tobys and GrainCorp. 

The silos are managed by GrainCorp and continue to be a significant landmark in the region, being visible from parts of the Warrego Highway to the north.  

  • Viewing and Parking Area Works

    Traffic management will be in place as required throughout the duration of the works.

  • Viewing Precinct Consultation

    Council sought community feedback on the proposed viewing precinct for the planned Silos Mural from Wednesday 17 April to Wednesday 10 May, 2023. See the Document Library for the Consultation Report.

  • Evaluation of Community Consultation

    Council will analyse the community's responses to the survey and pop-up consultations and prepare an Artist's Brief ready for Expression of Interest from suitably experienced artists. 

    See the Document Library for the consultation report and analysis.