The $500,000 upgrade to Gatton Skatepark is now complete, and is open for use. The official Opening will take place Saturday 18 June along with a regional skate contest.
Click here for more details.
Council has obtained grant funding to undertake upgrades which are scheduled for Summer 2021-2022. One of the purposes of the Master Plan and consultation processes was to provide the necessary evidence to support major funding submissions for significant upgrades. All projects seeking Council spending need to be weighed against a range of community priorities.
The first stage of the consultation (in April and May 2019) will be gathering information on types of use and preferred elements at the region's skateparks. The results of this consultation will be used by a skatepark designer to come up with concept plans that reflect the feedback from skatepark users, within budget and environmental limitations. The concept design for Gatton Skatepark Upgrades will be added to this site once available from the contractor.
Council receives requests from time to time for shade at some skateparks and will consider installing shade structures subject to the following:
Council is not currently considering any new skateparks in the region in the next 5 years based on the following factors:
Lockyer Valley Regional Council's skateparks are at:
Gatton Skatepark will receive a major upgrade commencing early January 2022 (weather permitting), effectively doubling the skateable surface.
Upgrades include a bowl and new street skating features and integrates with the existing skatepark. Additionally, lighting will be installed to allow for evening skating.
Note that the skatepark will be completely closed during construction which is expected to occur from January 2022 until mid-May 2022 (weather permitting). Please note that the February flood event damaged some works in progress and have resulted in a further delay to April. See the bottom of the home page for the location of other local skateparks.
Council has received grant funding from the Australian Government's Drought Communities Programme to undertake upgrades at Forest Hill and Gatton Skateparks. Upgrades include:
Council is currently investigating an option to reseal and extend the bitumen BMX section of the Laidley Skatepark.